Home / Trades / Electrical

Electrical: what bids leave out

Electrical bids often differ because each bidder drew the line in a different place, not because one priced the work better. One carries temporary power, fire alarm and site lighting. Another prices the building only and leaves out the utility charges, trenching, low-voltage rough-in and owner-furnished equipment hookups. Get them all on the same line list before you compare.

Level your electrical bids with this checklist →

Standard scope checklist

Send this to every bidder and ask them to mark each line Included, Excluded or give an Add $. Silence is not inclusion.

#Scope item
1Utility service coordination and utility company charges
2Service entrance, metering and main switchgear
3Temporary power & lighting during construction (install, maintain, remove)
4Distribution: panels, feeders and transformers per drawings
5Branch circuits, devices and wiring methods per spec (conduit vs. MC cable)
6Light fixtures: furnished by whom, installed by whom
7Lighting controls: sensors, dimming, programming and commissioning
8Exit and emergency lighting
9Mechanical equipment power connections (HVAC, pumps, water heaters)
10Owner-furnished equipment connections (kitchen, signage, process equipment)
11Fire alarm system: devices, panel, programming, permit
12Low-voltage rough-in: boxes, conduit and pull strings for data / security / AV
13Site lighting, pole bases and trenching
14Trenching, backfill and underground conduit
15Generator, transfer switch and connections (if any)
16Grounding and bonding
17Demolition and make-safe of existing electrical
18Coring, cutting and patching for electrical work
19Firestopping of electrical penetrations
20Testing, labeling, arc-flash study and labels if required
21Permits and inspection fees
22Lifts and access equipment
23After-hours or shutdown work in occupied spaces
24As-built drawings and O&M manuals
25Sales tax, bond and prevailing wage

Common exclusions and how they are worded

ExclusionTypical wordingWhy it mattersTypical cost to cover
Utility company charges
  • “Excludes utility company fees and charges”
  • “Primary service by utility”
  • “Transformer pad by others”
The utility's own work and fees, plus the transformer pad and primary conduit, are often excluded. They're usually owner costs, so get them in the budget early.TBD
Temporary power
  • “Excludes temporary power”
  • “Temporary power by GC”
Someone has to provide, maintain and remove construction power and lighting. If no bidder carries it, it lands on you or your GC.TBD
Fire alarm
  • “Fire alarm by others”
  • “Fire alarm rough-in only”
  • “Excludes fire alarm programming”
Fire alarm is often a separate design-build specialty. Some electrical bids include it all, others only the conduit. This alone can explain a big spread between bids.TBD
Low-voltage rough-in
  • “Excludes low voltage”
  • “Data / security by others”
  • “Excludes boxes and pull strings for low voltage”
Even when cabling is by a low-voltage sub, someone has to set boxes and conduit in the walls before drywall. Make sure one bid carries it.TBD
Trenching & site work
  • “Excludes trenching and backfill”
  • “Excludes site lighting”
  • “Excludes pole bases”
Site lighting and underground feeders need trenches and bases. These can fall between the electrician, the grader and the concrete sub.TBD
Owner-furnished equipment
  • “Connections to owner-furnished equipment by others”
  • “Excludes equipment not shown on E-sheets”
Kitchen, signage, IT and process equipment all need power and final connections. If the list isn't spelled out, expect change orders.TBD
Cutting, patching & firestopping
  • “Excludes patching and painting”
  • “Firestopping by others”
  • “Excludes core drilling”
Penetrations through rated walls must be firestopped, and openings must be patched. These are common exclusions across all MEP trades.TBD
Lighting controls & commissioning
  • “Excludes lighting control programming”
  • “Excludes commissioning”
Code-required lighting controls need start-up and programming. A bid that only hangs the sensors leaves you with lights that don't work right.TBD
Testing & arc-flash
  • “Excludes third-party testing”
  • “Excludes arc-flash study and labeling”
If your spec or insurer requires testing or an arc-flash study, it needs to be priced. Ask whether it's in the bid.TBD
After-hours & shutdowns
  • “Normal working hours only”
  • “Excludes overtime / premium time”
Work in occupied buildings often means night or weekend shutdowns. A daytime-only bid isn't comparable to one that prices the real schedule.TBD

“Typical cost to cover” is TBD. We will publish ranges only once we have real, sourced data. Until then, use your own estimate or a confirmed add price from a bidder.

Questions to ask bidders

  1. Where does your scope start at the utility service, and are any utility company charges included?
  2. Is temporary power and lighting included? Who maintains it, and who pays for the power used?
  3. Is the fire alarm system included in full (design, devices, panel, programming, permit) or rough-in only?
  4. Are low-voltage boxes, conduit and pull strings included?
  5. Which owner-furnished equipment connections did you include? Please list them.
  6. Is site lighting included, including trenching and pole bases?
  7. Did you price conduit or MC cable for branch circuits, and does that match the spec?
  8. Are cutting, patching and firestopping of your penetrations included?
  9. Does your price assume normal hours? What would after-hours shutdowns add?
Placeholder

Bid-ready electrical contractors

Contractors who agree to price against the standard checklist above, with exclusions spelled out line by line. Listings are not live yet.

Featured listing

Your company · City, ST

Bids on the BidGaps checklist

Featured listing

Your company · City, ST

Bids on the BidGaps checklist

List your company →